Main Street Sidewalk / Ramp Improvement Project

  1. December 11, 2020 - Project Update Number 9
  2. December 4, 2020 - Project Update Number 8
  3. November 25, 2020 - Project Update Number 7
  4. November 20, 2020 - Project Update Number 6
  5. November 6, 2020 - Project Update Number 5
  6. October 30, 2020 - Project Update Number 4
  7. October 30, 2020 - Project Update Number 3

All - thank you again for your continued patience during this project. The end is near! The work to be completed on December 11, 2020, and planned for the week of December 14, 2020 (some work weather dependent) is as follows:

  • The crosswalk at Puritan and Library Lane/Captain's Table that was moved westerly approximately 75 feet to 579 Main Street connecting to 578 Main Street (entrance to the Longfellow/Sara Campbell building) will be eliminated. It was determined today that it is too challenging to meet the slope needed for an Americans with Disabilities Act (ADA) compliant entrance to 578 Main Street. It had ADA compliance challenges at its original location as well. It will not be replaced. It is anticipated that work in that area will be completed end of the day on Friday, December 11, 2020. Also on December 11, 2020, miscellaneous hot mix asphalt (HMA) work will be done to complete any remaining driveway aprons.
  • By end of the day on December 15, 2020, hopefully, we will have all miscellaneous HMA work and clean-up completed.

Again, thank you so much for your patience! If you have any questions, please call me at 508-945-5105 or email Jill R. Goldsmith or call Public Works Director Thomas Temple at 508-945-5155 or email Robert Faley. Thank you!

Jill R. Goldsmith, Chatham Town Manager, ICMA-CM